CEEW-CEF Intelligence
The tool helps RE project developers and corporate (commercial/industrial) electricity consumers to determine open access charges and landed tariffs for different states under various scenarios.
Note: Values are expressed as percentage of open access charges waived off for solar/wind open access. 0% implies no waiver, while 100% implies a full waiver of a particular charge. For banking, actual charges are captured instead of waiver.
Note: Values are expressed as percentage of open access charges waived off for solar/wind open access. 0% implies no waiver, while 100% implies a full waiver of a particular charge. For banking, actual charges are captured instead of waiver.
Distribution (Wheeling) charges
Transmission charges
Cross subsidy
Additional surcharge
Bankinig charge
Andhra Pradesh
Distribution (Wheeling) charges
0%
Transmission charges
0%
Cross subsidy
Solar/Wind/Hybrid (Captive) - 100%
Solar/Wind/Hybrid (Third Party) - 0%
Additional surcharge
100% (Not levied)
Banking charges
Banking not allowed
Chhattisgarh
Distribution (Wheeling) charges
100%
Transmission charges
100%
Cross subsidy
Solar/Wind - 100%
Solar/Wind - 50%
Additional surcharge
100% (Not levied)
Banking charges
2% of energy banked
Gujarat
Distribution (Wheeling) charges
Solar (Captive/Third party) - 0%
Hybrid (Captive) - 50%
Hybrid (Third party) - 0%
Wind (Captive) - 50%
Wind (Third party) - 0%
Transmission charges
0%
Cross subsidy
Solar/Wind/Hybrid (Captive) - 100%
Solar (Third party) - 0%
Wind/Hybrid (Third party) - 50%
Additional surcharge
Solar/Wind/Hybrid (Captive) - 100%
Solar (Third party) - 0%
Wind/Hybrid (Third party) - 50%
Banking charges
Solar - 1.5 INR/kWh
Hybrid - No charges
Wind (Third party) - Banking not allowed
Haryana
Distribution (Wheeling) charges
0%
Transmission charges
0%
Cross subsidy
Solar/Wind (Captive) - 100%
Solar/Wind (Third Party) - 0%
Additional surcharge
Solar/Wind (Captive) - 100%
Solar/Wind (Third Party) - 0%
Banking charges
1.5 INR/kWh
Jharkhand
Distribution (Wheeling) charges
Solar/Wind (Captive) - 50%
Solar/Wind (Third Party) - 0%
Transmission charges
0%
Cross subsidy
Solar/Wind (Captive) - 100%
Solar/Wind (Third Party) - 0%
Additional surcharge
100% (Not levied)
Banking charges
2% of energy delivered at the point of drawl
Karnataka
Distribution (Wheeling) charges
50%
Transmission charges
50%
Cross subsidy
Solar/Wind (Captive) - 100%
Solar/Wind (Third Party) - 0%
Additional surcharge
Solar/Wind (Captive) - 100%
Solar/Wind (Third Party) - 87%
Banking charges
Banking not allowed
Madhya Pradesh
Distribution (Wheeling) charges
0% (GoMP to provide a grant of 4% in terms of energy injected to wind/solar projects)
Transmission charges
0%
Cross subsidy
Solar/Wind (Captive) - 100%
Solar/Wind (Third Party) - 0%
Additional surcharge
0% (Additional surcharge also applicable for captive)
Banking charges
Not allowed (or at the discretion of discoms)
Maharashtra
Distribution (Wheeling) charges
0%
Transmission charges
-100% (STU charges for RE are twice of that for conventional fuel)
Cross subsidy
Solar/Wind (Captive) - 100%
Solar/Wind (Third Party) - 0%
Additional surcharge
0% (Additional surcharge also applicable for captive)
Banking charges
2% of banked energy
Odisha
Distribution (Wheeling) charges
80%
Transmission charges
80%
Cross subsidy
100%
Additional surcharge
100% (Not levied)
Banking charges
Banking not allowed
Rajasthan
Distribution (Wheeling) charges
Solar (Captive/Third party) - 50%
Solar+storage/Wind/Hybrid/Repowered wind (Captive/Third party) - 75%
Transmission charges
Solar (Captive/Third party) - 50%
Solar+storage/Wind/Hybrid/Repowered wind (Captive/Third party) - 75%
Cross subsidy
100% (Not levied)
Additional surcharge
Solar/Wind (Captive) - 100%
Solar/Wind (Third Party) - 0%
Banking charges
10% of energy delivered at the point of drawl
Tamil Nadu
Distribution (Wheeling) charges
50%
Transmission charges
50%
Cross subsidy
Solar/Wind (Captive) - 100%
Solar (Third Party) - 70%
Wind (Third Party) - 60%
Additional surcharge
100% (Not levied)
Banking charges
Solar - Not allowed
Wind - 14% of energy banked (Banking not allowed for wind third party)
Uttar Pradesh
Distribution (Wheeling) charges
Solar (Captive/Third party) - 100% (inter-state), 50% (Intra-state)
Wind (Captive/Third party) - 0%
Transmission charges
Solar (Captive/Third party) - 100% (inter-state), 50% (Intra-state)
Wind (Captive/Third party) - 0%
Cross subsidy
Solar/Wind (Captive) - 100%
Solar (Third party) - 100%
Wind (Third party) - 0%
Additional surcharge
100% (Not levied)
Banking charges
Solar - 12% of energy banked
Wind - 6% of energy banked
West Bengal
Distribution (Wheeling) charges
0%
Transmission charges
0%
Cross subsidy
0%
Additional surcharge
0%
Banking charges
Not allowed
Distribution (Wheeling) charges
0%
Transmission charges
0%
Cross subsidy
Solar/Wind/Hybrid (Captive) - 100%
Solar/Wind/Hybrid (Third Party) - 0%
Additional surcharge
Solar/Wind/Hybrid (Captive) - 100%
Solar/Wind/Hybrid (Third Party) - 0%
Banking charges
Banking not allowed
Distribution (Wheeling) charges
100%
Transmission charges
100%
Cross subsidy
Solar/Wind - 100%
Solar/Wind - 50%
Additional surcharge
Solar/Wind - 100%
Solar/Wind - 50%
Banking charges
2% of energy banked
Distribution (Wheeling) charges
Solar (Captive/Third party) - 0%
Hybrid (Captive) - 50%
Hybrid (Third party) - 0%
Wind (Captive) - 50%
Wind (Third party) - 0%
Transmission charges
0%
Cross subsidy
Solar/Wind/Hybrid (Captive) - 100%
Solar (Third party) - 0%
Wind/Hybrid (Third party) - 50%
Additional surcharge
Solar/Wind/Hybrid (Captive) - 100%
Solar (Third party) - 0%
Wind/Hybrid (Third party) - 50%
Banking charges
Solar - 1.5 INR/kWh
Hybrid - No charges
Wind (Third party) - Banking not allowed
Distribution (Wheeling) charges
0%
Transmission charges
0%
Cross subsidy
Solar/Wind (Captive) - 100%
Solar/Wind (Third Party) - 0%
Additional surcharge
Solar/Wind (Captive) - 100%
Solar/Wind (Third Party) - 0%
Banking charges
1.5 INR/kWh
Distribution (Wheeling) charges
Solar/Wind (Captive) - 50%
Solar/Wind (Third Party) - 0%
Transmission charges
0%
Cross subsidy
Solar/Wind (Captive) - 100%
Solar/Wind (Third Party) - 0%
Additional surcharge
Solar/Wind (Captive) - 100%
Solar/Wind (Third Party) - 0%
Banking charges
2% of energy delivered at the point of drawl
Distribution (Wheeling) charges
50%
Transmission charges
50%
Cross subsidy
Solar/Wind (Captive) - 100%
Solar/Wind (Third Party) - 0%
Additional surcharge
Solar/Wind (Captive) - 100%
Solar/Wind (Third Party) - 0%
Banking charges
Banking not allowed
Distribution (Wheeling) charges
0% (GoMP to provide a grant of 4% in terms of energy injected to wind/solar projects)
Transmission charges
0%
Cross subsidy
Solar/Wind (Captive) - 100%
Solar/Wind (Third Party) - 0%
Additional surcharge
Solar/Wind (Captive) - 100%
Solar/Wind (Third Party) - 0%
Banking charges
Not allowed (or at the discretion of discoms)
Distribution (Wheeling) charges
0%
Transmission charges
-100% (STU charges for RE are twice of that for conventional fuel)
Cross subsidy
Solar/Wind (Captive) - 100%
Solar/Wind (Third Party) - 0%
Additional surcharge
Solar/Wind (Captive) - 100%
Solar/Wind (Third Party) - 0%
Banking charges
2% of banked energy
Distribution (Wheeling) charges
80%
Transmission charges
80%
Cross subsidy
100%
Additional surcharge
100%
Banking charges
Banking not allowed
Distribution (Wheeling) charges
Solar (Captive/Third party) - 50%
Solar+storage/Wind/Hybrid/Repowered wind (Captive/Third party) - 75%
Transmission charges
Solar (Captive/Third party) - 50%
Solar+storage/Wind/Hybrid/Repowered wind (Captive/Third party) - 75%
Cross subsidy
100% (Not levied)
Additional surcharge
100% (Not levied)
Banking charges
10% of energy delivered at the point of drawl
Distribution (Wheeling) charges
50%
Transmission charges
50%
Cross subsidy
Solar/Wind (Captive) - 100%
Solar (Third Party) - 70%
Wind (Third Party) - 60%
Additional surcharge
Solar/Wind (Captive) - 100%
Solar (Third Party) - 70%
Wind (Third Party) - 60%
Banking charges
Solar - Not allowed
Wind - 14% of energy banked (Banking not allowed for wind third party)
Distribution (Wheeling) charges
Solar (Captive/Third party) - 100% (inter-state), 50% (Intra-state)
Wind (Captive/Third party) - 0%
Transmission charges
Solar (Captive/Third party) - 100% (inter-state), 50% (Intra-state)
Wind (Captive/Third party) - 0%
Cross subsidy
Solar/Wind (Captive) - 100%
Solar (Third party) - 100%
Wind (Third party) - 0%
Additional surcharge
Solar/Wind (Captive) - 100%
Solar (Third party) - 100%
Wind (Third party) - 0%
Banking charges
Solar - 12% of energy banked
Wind - 6% of energy banked
Distribution (Wheeling) charges
0%
Transmission charges
0%
Cross subsidy
0%
Additional surcharge
0%
Banking charges
Not allowed